The client requested the installation of three dedicated 240V circuits to power machinery.
Our technician piped and pulled one 60 AMP and two 70 AMP circuits through 130 feet of EMT from a 240V 3-phase panel to a junction box. The circuits were then extended from the junction box to customer-supplied disconnects, and connected to the machinery. The existing wiring in the warehouse was found to be undersized and not up to code, so new wiring was installed to meet National Electrical Code standards, ensuring safe and proper operation of the client’s equipment.